Airport

Manchester Airport

Equipment
1 x Tempair Heat Pump.

Total air volume: 3.1m3/s
Serving: Passenger Lounge
Control: Supply air, constant volume, supply air scheduling.

The roof area designated for the plant, restricted the access time for labour, due to aircraft movements. The Tempair offered reduced site labour as the unit had been commissioned at the factory and only required electrical connection on site. The unit supplied tempered air to the passenger lounge. The area was served with room internal heating and cooling units. To provide additional cooling and free cooling the supply air setpoint was scheduled to reduce as the return temperature air increased. Cooling recovery was also available

 